Interior Doors for Renovation Projects: What to Put in Your RFQ
A renovation RFQ is harder than a new-build one: the openings already exist, and they are rarely square. The fields, measurements and decisions that turn a door enquiry into an accurate quotation.
- A renovation RFQ is specified against openings that already exist — walls that are not plumb, frames that are not coming out, lifts and stairwells that cap module size — so the measurement section matters more than the style section.
- Ten fields turn a vague door enquiry into an accurate quotation: door schedule, measured openings, wall conditions, frame preference, swing, hardware, finish matching, phasing, access route and destination requirements.
- Group the openings into one door schedule instead of describing them in prose — it is faster to quote, and it makes the exposure differences between rooms visible.
- REMUCH produces interior doors to your drawings with no MOQ and a confirmed 30–60 day cabinetry production window; every open field is settled in writing before production.
Why a renovation RFQ is different from a new-build one
An interior door RFQ for a renovation project is specified against conditions that a new-build enquiry never has: the openings already exist, the walls around them are rarely plumb, some frames are staying and some are going, and the delivery route runs through a finished or occupied building. A new-build buyer can work from architect drawings with generous tolerances; a renovation buyer is asking a factory half a world away to produce doors that must meet real, measured, slightly imperfect openings on a specific floor of a specific building. That is not a problem — it is simply a different brief, and it rewards precision over enthusiasm.
This guide is a practical RFQ checklist for designers, contractors and homeowners specifying made-to-measure interior doors for a renovation or retrofit — room doors and hidden doors alike from our interior door line, produced to drawings like the rest of the board-based product lines. Send what you have; a sketch with measured dimensions is a valid starting point, and every open field is settled in writing before production rather than assumed.

The anatomy of a door RFQ
Before the details, the structure. The enquiries that quote fastest and most accurately share one habit: the openings are grouped into a single door schedule — a table with one row per door — instead of being described in prose. A schedule makes the project legible at a glance: how many doors, which rooms, which finishes, where the exposure differs. It also maps directly onto the format the production team works from, so nothing gets re-typed and nothing gets lost in translation.
| # | RFQ field | What to provide |
|---|---|---|
| 01 | Door schedule | One row per opening: position/room, quantity, and any special note (bathroom, hidden door, oversized) |
| 02 | Measured openings | Width and height at several points, wall thickness, and the finished floor level for each opening |
| 03 | Wall conditions | Stud, masonry or partition; existing frame staying or being replaced; plumb or out-of-plumb, with the deviation noted |
| 04 | Frame preference | New frame and architrave from the factory, or doors leaf-only into existing frames |
| 05 | Swing and handing | Which way each door opens and which side the handle is on — decide per opening, not per project |
| 06 | Hardware | Hinges, lock or latch bodies, handles, closers — brands or models if specified, or ask for a recommendation |
| 07 | Finish matching | Whether door finishes must match wardrobes, kitchens or wall panels in the same order |
| 08 | Delivery phasing | Which doors are needed for which phase — renovation programmes usually run room by room |
| 09 | Access route | Lift cabin or stairwell geometry, landing and room door widths, and the tightest point |
| 10 | Destination requirements | Any standard, grade or documentation the destination market expects — stated during quoting |
Fields 01–07 decide the product. Fields 08–10 decide the logistics and the compliance — and in renovation projects they are the ones most often left out, usually at the cost of a change order later.
Measure the openings as they are, not as the plan says
The single highest-value section of a renovation RFQ is the measurement. Renovation walls move, plaster builds up unevenly, and finished floor levels shift by centimetres between rooms. A door leaf produced to a nominal opening can end up with visible gaps at one jamb and an interference at the other:
- Measure each opening in several places — width at the floor, at mid-height and at the top; height on both sides. If the numbers differ, write down all of them, not just the largest.
- Record the wall thickness at each opening — frames, architraves and hidden-door systems are all designed against it.
- Mark the obstructions. Skirting, sockets, switches, pipes and any beam change frame details and hardware positions.
- State the finished floor level for each room, especially where flooring is being replaced in some rooms and not others — the door bottom clearance is calculated against it.
- Note what was measured on site versus taken from a drawing, so everyone knows which numbers are authoritative.
One scope boundary to state plainly: on-site measuring and installation are not part of our scope for overseas orders. The dimensions in your RFQ are the ones the quotation and the production drawings are built on, which is exactly why this section deserves the care above. Anything that remains open — tolerances, scribe details, clearance allowances — is confirmed in writing with your order.

Frame or leaf-only: the decision that shapes the quotation
Renovation projects split into two very different door packages, and deciding which one you are buying belongs in the RFQ, not in the quotation:
| Approach | When it fits | What the RFQ must include |
|---|---|---|
| Full package — new frames, architraves and leaves | Frames are coming out, or openings are being re-formed | Wall thickness per opening, wall condition, architrave style, and the plumb deviations noted above |
| Leaf-only — doors into existing frames | Frames are sound and staying; budget or programme favours reuse | Existing frame internal dimensions measured in several places, hinge and lock positions, rebate or stop details |
Leaf-only orders are common in renovation and no less "custom" — but they shift the precision burden onto the frame measurements, because the new leaf has to meet the old frame exactly. Where the existing frames vary between rooms, say so: a schedule that flags two slightly different frame sizes is quotable, while a discovery at delivery is not a schedule at all.
Hidden doors, wet rooms and other special openings
Most of the schedule is straightforward room doors, but renovation briefs almost always contain a few special cases — and special cases are where an unspecified detail becomes a production assumption. Flag each of these explicitly:
- Hidden / flush doors — the concealed frame integrates with the wall build-up, so the wall construction, thickness and finishing sequence all belong in the RFQ. Coordination with wall panelling from the same production family is common; see how the five product lines coordinate.
- Bathroom and wet-area doors — exposure drives the construction questions; our humid-climate door checklist covers exactly what to ask.
- Oversized or non-standard openings — older buildings and renovated layouts often produce openings above standard heights; flag them so structural and hardware implications are priced rather than assumed.
- Doors that must match existing furniture — where a renovation adds doors to a home that already has our wardrobes or panelling, the finish specification should reference the previous confirmed spec so the batches match.
Phasing, packing and the last ten metres
Renovation programmes rarely take delivery of everything at once, and the building itself constrains what can physically arrive. Both points belong in the RFQ:
- Phasing: say which doors are needed for which phase. There is no MOQ on the cabinetry lines, so a phase-by-phase delivery is a normal order pattern — repeat orders can reuse the confirmed specification to keep later batches consistent.
- Access route: record the lift cabin dimensions or stairwell geometry, landing and room door widths, and flag the tightest point. One measurement caps the maximum packed module size more than any other number in the brief.
- Packing follows the route and the programme: packing method and loading guidance are confirmed in writing against your order — which is why the route belongs in the RFQ from the start, not in a phone call after the quotation.
- Work backwards from the site date: production runs within the confirmed 30–60 day cabinetry window with the start point stated in your quotation, and shipping and receiving time sit on top of it. Renovation schedules fail at the receiving end far more often than at the production end.
What happens after you send it
The process is deliberately short: send the door schedule and the measured openings → receive a written quotation with every open detail confirmed → settle frame approach, hardware and finish → production and packing within the confirmed window. Requirements raised during quoting are specification lines with documentation; the same requirements raised after the quotation is agreed are change orders. If a question is not covered, the FAQ page collects the answers buyers most often need before ordering — and the standard throughout is the same one we hold our own figures to: if it matters to your purchasing decision, it is confirmed in writing with evidence.
Frequently asked questions
Do you produce interior doors for renovation projects overseas?
Yes — we produce made-to-measure interior doors for export and confirm packing, loading guidance and shipment planning in writing with your order. Destination-market requirements should be raised during quoting so they can be confirmed with documentation.
Do you measure on site or install the doors?
No. On-site measuring and installation are outside our scope for overseas orders. The dimensions in your RFQ form the basis of the quotation and the production drawings, which is why the measurement checklist matters.
Can I order door leaves only, into my existing frames?
Yes — leaf-only into existing frames is a common renovation pattern. The RFQ then needs the existing frame dimensions measured in several places, plus hinge and lock positions and rebate details, so the new leaf meets the old frame exactly.
How do you handle phased deliveries for a renovation?
Phased delivery is a normal order pattern — there is no MOQ on our cabinetry lines. State which doors are needed for which phase, and repeat orders can reuse the confirmed specification so later batches stay consistent.
Can the doors match my wardrobe and wall panel finishes?
Yes. Interior doors, wardrobes, kitchen cabinets and wall panels belong to the same board-based production family, so one finish specification can run across them in the same order. Aluminium windows are a separate metal-and-glass line.
How long does production take?
The confirmed cabinetry production window is 30–60 days, with the exact start point and schedule stated in your written quotation — work backwards from your site date to include shipping and receiving.